Replace 8 out-of-warranty DPW vehicles: 3 dump trucks, 2 street sweepers, 3 utility pickups.
Schedule
- Planned start
- Jan 31, 2026
- Actual start
- —
- Planned completion
- Aug 30, 2026
Budget & funding
- Planned budget
- $1,250,000
- Approved budget
- $1,250,000
- Funding source
- capital improvement
- Type
- Capital project