Capitalactivehigh

Central Avenue Complete Streets Reconstruction

DPW-2025-001 · Department of Public Works

About this project

Reconstruction of Central Ave including ADA-compliant sidewalks, protected bike lanes, and stormwater upgrades.

Schedule

Planned start
Mar 31, 2025
Actual start
Planned completion
Sep 29, 2026

Budget & funding

Planned budget
$4,250,000
Approved budget
$4,250,000
Funding source
bond
Type
Capital project